top of page

METHOD OF PROTECTING A METAL PIPE IN FEF INSULATION PENETRATING WALL AND FLOOR ACCORDING TO ETA-17/1061

1.png

1 - rigid wall thickness B = min. 150 mm
2 - metal pipe, diameter "D" and pipe wall thickness "t"
3 - continuous insulation made of flexible elastomeric foam (FEF), 
     thickness "G", nominal density 45 - 70 kg/m3 and reaction to fire class   
     BL-s2, d0 according to EN 13501-1
4 - the gap between the pipe insulation and the partition with a maximum 
     width of u = 25 mm, filled with mineral wool with a density of min. 60 
     kg/m3 and closed with gypsum mortar with a thickness of min. 5 mm
     or filled cement mortar
5 - gypsum mortar with a thickness of g1 = 5 mm
6 - Piro Multitube PM (inside) with dimensions [h x s], centrally located inside the wall
7 - cable tie or adhesive tape

Technical drawing 1

1 - reinforced concrete floor with a thickness of B = min. 150 mm
2 - metal pipe, diameter "D" and pipe wall thickness "t"
3 - continuous insulation made of flexible elastomeric foam (FEF), 
      thickness "G", nominal density 45 - 70 kg/m3 and reaction to fire 
      class BL-s2, d0 according to EN 13501-1
4 - Piro Multitube PM (inside) [h x s] mm; placed in distance l = 15 ± 5 
      mm from the underside of the floor
5 - clamp band or adhesive tape
6 - the gap between the pipe insulation and the partition with the 
     maximum width u = 25 mm, filled with cement mortar

2.PNG
Technical drawing 2
Steps 1 - 5
Multitube rury metalowe w izolacji kauczuk 1.png

Read in the tables the length of Piro Multitube PM for the given diameter and the type of pipe, measure it and cut it with a knife.

Wrap the cut tape around the pipe insulation. Follow strictly the number of wraps given in the tables.

Multitube rury metalowe w izolacji kauczuk 2.png
Multitube rury metalowe w izolacji kauczuk 3.png

Secure the Piro Multitube PM with a cable tie or adhesive tape and slide it inside the partition. Location of the tape inside the opening - central position along the wall axis or 15 ± 5 mm from the bottom of the floor.

Fill the space between the pipe and the partition with cement mortar.

Multitube rury Metalowe w izolacji Kauczuk 4.png
Multitube rury metalowe w izolacji kauczuk 5.png

Mark the completed penetration seal with the attached label, mark Piro Multitube PM on it, enter the date and name.

Have questions?

A qualified team of Pirosystem can help in the selection of passive fire protection system and other fire protection solutions.

bottom of page